New Electricity Connection: Apply Online
Every DISCO now takes new-connection applications through one official portal — ENC. Here's the process end to end, and the traps to avoid.
Official portal:applications for all 11 DISCOs go through PITC's ENC system.
Open ENC Portal (enc.com.pk) →Official PITC service — PakBills is not involved in processing applications.
The process, step by step
- Apply on ENC — choose your DISCO and connection type (domestic, commercial, industrial, agricultural), fill the form, upload CNIC and ownership/tenancy documents. Note the tracking ID.
- Site survey — the sub-division verifies the premises, distance from the transformer and required load.
- Demand notice — the official cost sheet (security deposit + service-connection charges). Pay it at the designated bank; keep the receipt.
- Wiring test & meter installation — after payment clears, the meter is installed and the connection energised.
- First bill — arrives within a cycle and carries your permanent reference number; from then on, check it like any bill via the bill checker.
Traps to avoid
- Paying anyone other than the bank against the demand notice. "Speed money" agents around DISCO offices have no official standing.
- Wrong load declaration — understating load to save on charges leads to detection bills later; overstating raises your costs now.
- Applying under disputes — unresolved arrears on a previous connection at the same premises will block the application; settle first (see complaints guide for disputed arrears).
Frequently asked questions
- How long does a new electricity connection take?
Officially, standard single-phase connections are to be processed within about a month of a complete application and payment; in practice timelines vary by DISCO workload and whether your street already has a suitable transformer. Track your application on the ENC portal with your tracking ID. - What documents do I need?
Typically: CNIC of the applicant, proof of ownership or a registered rent deed for the premises, a copy of a neighbour's bill (helps locate the feeder/transformer), and the wiring completion/test report where required. The ENC portal lists the exact set for each connection type. - What does a new connection cost?
You pay the official demand notice: a security deposit plus service-connection charges that depend on load and how much cable/equipment your connection needs. Anyone quoting a fixed 'total price' before the demand notice is issued is guessing — or worse. Pay only against the official demand notice at a bank. - Can I apply without going to a DISCO office?
Yes — the ENC portal (enc.com.pk) accepts online applications for all PITC DISCOs: fill the form, upload documents, and track status with the ID it issues. Site inspection and meter installation still happen physically, but the paperwork is online. - My reference number hasn't appeared after meter installation — normal?
Your permanent reference number is issued with the first bill, which can take a full billing cycle after energisation. Once that first bill arrives, the number works on the PITC portal like any other connection.